I'AM ON
  • Light weight, easy to transport.
  • Smooth bore ensures higher flow.
  • UPVC is rustproof material therefore bore diameter remains constant.
  • Long working life.
  • Cost effective.
Aquafit UPVC pipes are made from highest grade quality resin. These pipes & fittings are mainly used for water supply in agriculture, drip irrigation & sprinkler lines etc as well as for drinking water distribution. However, these can also be used in cable ducting, ventilation pipe lines & slurry lines etc.

Pipes

Agri Pipes – ISI

High Pressure Pipe – ISI

Agri Pressure & Non Pressure Pipes

Note: Pipes available with ISI mark except 400mm.

Fittings

Ball valves

UPVC Brass Insert Fittings

UPVC Fabricatted Fittings

  • Febricated Coupler

  • Febricated Bend

  • Repair Coupler

UPVC Fittings

  • Coupler 10kg / Heavy

  • Coupler PN 10

  • Coupler LW

  • Coupler Prestige

  • Elbow

  • Elbow (PN 10 / PN 6)

  • Elbow LW

  • Elbow Prestige

  • Tee (Conceal / 10kg / Heavy)

  • Tee (PN 10 / PN 6)

  • Tee LW

  • Tee Prestige

  • End Cap PN 6

  • End Cap (LW / LW Collar)

  • End Cap Threaded

  • Service Saddle

  • M. T. A.

  • F.T.A

  • Tail Piece

  • Flange

  • Reducer

  • Reducing Bush

  • Reducing Elbow

  • Reducing Tee

  • Four Way Tee

  • Reducing M. T. A.

  • Reducing F. T. A.

  • Thdreaded Elbow

  • Threaded Tee

Solvents

Solvent Cement

Specifications

Jointing Method

Process: Solvent Joint
DO'S
  • CUTTING

    It is imperative to mark the pipe from all sides so that pipe is cut with the help of a Hand Saw. It should be a right angle cut from all the sides. The cut piece should not be with burr on edges.

  • DEBURRING AND RIDGE REMOVAL

    Remove all the burrs and ridges accumulated on the inner as well as the outer edges of the pipe with the help of a deburring knife, file or abrasive paper.

  • CLEANING

    Thoroughly clean the pipe with dry cloth where the solvent cement is going to be applied, to avoid dust, dirt, oil, moisture and other foreign material during the installation process.

  • CHAMFERING

    After cutting, the pipe needs to be chamfered from the outer sides. It is advisable to provide approximately2 mm wide, 150 chamfer on spigot end.

  • DRYFIT TEST

    Before applying solvent cement, insert the pipe end into the socket of the next pipe or fitting to check that interference occurs at about 1/3 to 2/3 of the socket depth.

  • APPLICATION OF SOLVENT CEMENT

    Mark the pipe length to be inserted for jointing. Apply a liberal coat of solvent cement with the help of the brushon the marked surface.

  • JOINTING

    Push the pipe inside the fitting so that it goes inside it equally from all the sides. Wipe off excess solvent cement that comes out from all the edges. Hold the joint for to 2 minutes so that the jointing is perfect.

  • INSTALLATION AND COMMISSIONING

    a) Pipe line should be installed in proper alignment and along with necessary clamps.
    b) Pressure testing to be done before concealing work.
    c) Pressure testing may be carried out after a curing period of 24 hrs.

DONT'S
  • CUTTING

    Do not cut slant/unevenly.

  • DEBURRING AND RIDGE REMOVAL

    Do not proceed with the installation of pipe without deburring.

  • CLEANING

    Do not join the pipes without cleaning the pipe ends.

  • CHAMFERING

    Do not proceed with installation of pipe without chamfering.

  • DRYFIT TEST

    Do not apply solvent cement without dryfit test.

  • APPLICATION OF SOLVENT CEMENT

    Do not apply excess solvent cement on the pipe and do not use solvent cement by hand.

  • JOINTING

    Do not use a hammer or half push the pipe.

  • FOR THREADED JOINTS

    Don't over tighten with pipe wrench.

  • INSTALLATION AND COMMISSIONING

    a) Avoid loose joints and misalignments.
    b) Pressure testing should not be done before 24 hrs of curing.